新建項目(含水泥生產線,水泥粉磨站)建設順序流程圖
(以下敘述中,項目業主簡稱甲方,項目建設方簡稱乙方)
Flow chart of construction sequence of new projects (including cement production line and cement grinding station)
(In the following description, the owner of the project is referred to as Party A and the construction party is referred to as Party B)
甲方完成立項前的所有審批手續(含工可報告、能評報告、環評報告)。項目立項。
Party A shall complete all the examination and approval procedures (including project feasibility report, energy assessment report and environmental assessment report) before the project is established. Project approval.
乙方提供初步報價,初步報價中包括主機設備表,生產工藝流程圖。
Party B provides the preliminary quotation, which includes the list of main equipment and the flow chart of production process.
甲方接受乙方初步報價后,甲乙雙方簽訂《EPC合作框架協議》。
After Party A accepts Party B's initial offer, Party A and Party B sign《 the EPC Cooperation Framework Agreement》.
甲方支付乙方項目啟動資金。并提供給乙方包含坐標系地形圖。
Party A shall pay Party B's project start-up fund. It also provides topographic maps including coordinate system to Party B.
乙方根據甲方提供的地形圖進行工藝安排,提供給甲方初步工藝布置圖。
Party B shall arrange the process according to the topographic map provided by Party A and provide Party A with the preliminary process layout drawings.
甲乙雙方工藝布置圖確認。
Confirmation of Process Layout Drawings of Party A and Party B
乙方向甲方提供勘探點,由甲方進行勘探,提交勘探報告。
Party B shall provide exploration spot to Party A, and Party A shall conduct exploration and submit exploration reports.
項目進行初步設計。
Preliminary design of the project
初步設計的審查和批準。設計確定。
Examination and approval of preliminary design. The design is confirmed.
甲乙雙方簽訂《EPC項目總承包合同》
Party A and Party B sign the EPC Project General Contracting Contract